Procurement

Domain Objective: Deliver competitive, value-for-money procurements.”

WSA successfully completed several significant procurements. In July 2018, the Delivery Partner contract and the Project Management (Definition) contract were awarded to Bechtel Corporation (Bechtel). WSA also awarded the Early Earthworks contract to a joint venture between CPB Contractors and Lendlease (CPB/LL). The contract for the Experience Centre and Site Office was awarded in October 2018 to Watpac Limited.

Prior to issuing the Expression of Interest (EOI) documentation for the BEAC works, to ensure a competitive and value-for-money procurement, WSA undertook extensive market sounding to inform the best approach. The EOI process for BEAC Package 1A closed in September 2018 and the RFT was released in November 2018. The RFT closed in April 2019 and the contract is expected to be awarded in August 2019.

WSA started the procurement process for an Independent Certifier. The EOI process ended in April 2019 and WSA is anticipating an award date in August 2019.