Completing Land Preparation Works Stage 1
In December 2018, the demolition and early works on the land west of Moorebank Avenue was completed. All buildings were demolished, decontamination works undertaken, and underground services excavated and removed, enabling civil works to commence for full warehouse development of the site.
The next package of works will see the removal of 50 hectares of vegetation, allowing civil works to commence to prepare the existing ground for future fill and warehousing on the site.